+ Brownfield Engineering Technical Services

  • Mission:To do brownfield engineering project regarding commissioning, start-up and operation of:
  1. South Pars Gas Field Development Phases 17&18
  2. South Pars Gas Field Development Phases 20&21
  3. Bandar Abbas Gas Condensate Refinery
  • Client:Oil Industries' Commissioning and Operation Company (OICO)
  • Start Date:Sep-2016
  • End Date:Live
  • Project Value:1.6 Million USD

 

+ Installation, Commissioning, Startup, Operation and Maintenance of HVAC System of South Pars Gas Field Development Phases 22-24

  • Mission: Installation, Commissioning, Startup, Operation and Maintenance of HVAC System of South Pars Gas Field Development Phases 22-24
  • Client: Techno Energy Sepehr Kish (TESCO)
  • Start Date: May-2016
  • End Date: Live
  • Project Value: 4.3 Million USD

+ Commissioning and Start-up of South Pars Gas Field Development Phases 17&18

  • Mission: Specialist manpower supply for commissioning, startup and operation of South Pars Gas Field Development Phases 17&18
  • Client: Oil Industries' Commissioning and Operation Company (OICO)
  • Start Date: Aug-2014
  • End Date: Dec-2016
  • Project Value: 6.2 Million USD

 

 

+ Commissioning and Start-up of South Pars Gas Field Development Phases 20&21

  • Mission: Specialist manpower supply for commissioning, startup and operation of South Pars Gas Field Development Phases 20&21
  • Client: Oil Industries' Commissioning and Operation Company (OICO)
  • Start Date: Jan-2015
  • End Date: Mar-2017
  • Project Value: 4.4 Million USD

 

+ Commissioning and Start-up of Bandar Abbas Gas Condensate Refinery

  • Mission: Specialist manpower supply for Commissioning, Startup and Operation of Bandar Abbas Gas Condensate Refinery
  • Client: Oil Industries' Commissioning and Operation Company (OICO)
  • Start Date: Nov-2015
  • End Date: Mar-2017
  • Project Value: 5.5 Million USD

 

 

+ Construction of gas pipeline for Iran Mellas Factory (12km- 8in.)

  • Mission: Construction of a gas pipeline for Iran Mellas Factory (2km- 8in.)
  • Client: NIGC
  • Start Date: Sep-2005
  • End Date: Dec-2005
  • Project Value: 550,000 USD

+ Construction of gas pipelines and network for Golbahar Town - Phase 2 (20km – 2in-8in)

  • Mission: Construction of gas pipelines and network for Golbahar Town - Phase 2 (20km – 2in-8in)
  • Client: NIGC
  • Start Date: Jun-2003
  • End Date: Sep-2003
  • Project Value: 1.5 Million USD

+ Construction of four gas transmission pipelines to CNG stations in Ghoochan and Chenaran in Khorasan Province

  • Mission: of four gas transmission pipelines to CNG stations in Ghoochan and Chenaran in Khorasan Province
  • Client: NIGC
  • Start Date: July-2001
  • End Date: Dec-2002
  • Project Value: 250,000 USD

+ Construction of a gas pipeline in Khorasan Province (2km- 24in.)

  • Mission: Construction of gas pipeline in Khorasan Province (2km- 24in.)
  • Client: NIGC
  • Start Date: Jun-2001
  • End Date: Aug-2002
  • Project Value: 735,000 USD

+ Developing and construction of gas distribution network for 3th zone of National Gas Company of Khorasan (100km, 2-12 inch)

  • Mission: Developing and construction of gas distribution network for 3th zone of National Gas Company of Khorasan (100km, 2-12 inch)
  • Client: NIGC
  • Start Date: Feb-2002
  • End Date: Mar-2004
  • Project Value: 12.2 Million USD

+ Logestic Services for Saipem Employees

  • Mission: Facilitate Logestic of Saipem employees
  • Client: Saipem s.p.a
  • Start Date: 2016
  • End Date: Live
  • Project Value: 30,000 USD